Mediouna WWTP Expansion Doubles Capacity to 7,600 m³/day

A 109 million MAD project expands Mediouna's wastewater treatment plant from 3,800 to 7,600 m³ per day.

Mediouna WWTP Expansion Doubles Capacity to 7,600 m³/day

Image: medias24.com

The wastewater treatment plant (STEP) in Médiouna, Morocco, is undergoing a major expansion to double its treatment capacity. The project, with an estimated total cost of 109 million Moroccan dirhams (including taxes), aims to increase the plant's capacity from 3,800 cubic meters to 7,600 cubic meters per day.

This expansion is driven by the continuous increase in wastewater volumes due to population growth and urban development in the Médiouna region. The upgraded facility will help improve sanitation and environmental protection by treating a larger share of the area's wastewater.

The project includes the construction of new treatment units and the modernization of existing infrastructure. It is part of broader efforts by Moroccan authorities to enhance water resource management and meet growing demand for wastewater treatment services.

❓ Frequently Asked Questions

What is the new capacity of the Mediouna wastewater treatment plant?

The capacity will double from 3,800 to 7,600 cubic meters per day.

How much does the expansion project cost?

The project is estimated to cost 109 million Moroccan dirhams (including taxes).

Why is the expansion necessary?

The expansion is needed due to increasing wastewater volumes from population growth and urban development in the Médiouna region.